Sewer Betterment Explanation, Phase VI (revised)
Phase VI - History
Phase VI was voted in May 1996. That vote set the appropriation at $5.6 million, and set the geographic boundaries of Phase VI. In September, 2000, the Town voted a betterment assessment of $3,350,000, which represented what was stated to be 50% of the contracted total project cost of $6,700,000. Also voted was the formula to be used to calculate the betterments [acreage @ 75% / frontage @ 25%]. The original list of Phase VI properties was split, some designated as priorities (Attachment 1) and the rest undesignated; the priority properties were the only ones assessed betterments at first. The remaining properties on the original list were bettered in 2004. The total 50% betterment was $3.35 million.
In May 2002, ATM added 11 properties on
Attachment 3 shows the formula for calculating betterments in Phase VI.
To compare initial betterments to current estimates:
Understand that the 11 properties added in May 2002 will pay 100% of their calculated betterment at the completion of the project.
The properties that have been bettered at approximately 50% will see an approximate 83% increase to their total betterment at today’s project cost.
Taking
First assessed betterment = $16,259.07
Corrected assessment after additional properties added = $15,295.24
Overage = $ 963.83
Using $13,000,000 as total to re-calculate the total betterment (current actual appropriation is 13,026,295)
.92 acres (for 92 W.
390.885
250 linear feet frontage X 13,000,000 = 145,626.87 frontage
22,317.31
To then calculate the 75% acreage / 25% frontage, multiply acreage times 3 and frontage times 1 then divide by 4.
3(30,597.23) = 91,791.69
1(145,626.87) = 145,626.87
Total 237,418.56
Divide the total by 4 = $59,354.64 assessed betterment on $13,000,000
Original approximate 50% betterment for 92 W.
Expected 100% would have been $32,518.14; today the assessment will
be $59,354.64, a delta increase of $26,836.50 (or 82.53% increase).
Additional assessment will be $43,096.29.
We will likely need a consultant to manage the betterment work and calculations at completion of the project.